A new kind of load on the grid
India has about 2 GW of data centre capacity today. Forecasts for 2030 range from about 5 GW (S&P Global's base case) to 9 GW (IEEFA) and 12 GW (Wood Mackenzie), depending mainly on how much AI computing ends up being built in India rather than abroad.
The electricity figures matter more. S&P Global estimates that data centres used about 13 TWh in 2024, or 0.8% of India's electricity demand. By 2030 it expects that to reach about 57 TWh, roughly 2.6% of national demand. IEEFA's estimate is similar, at about 3%.
Data centres also use power differently from most industry. A typical heavy industrial plant draws perhaps 50-60% of its connected load on average. A data centre runs at 80-90%, around the clock, every day of the year. So one gigawatt of data centres puts about as much steady demand on the grid as two gigawatts of ordinary industrial connections. Several analysts now say power, not land, is the main constraint on where data centres get built.
That demand adds to a grid already under strain. In July, Power Minister Manohar Lal said national peak demand was heading towards 300 GW within a year, and named data centres, AI and electric vehicles as the main new sources of load.
The parks are being signed now
The projects are not hypothetical. On October 8, ReNew signed a Rs 70,000 crore MoU with the Maharashtra government for a 750 MW Green Integrated Data Centre Park across Panvel, Khalapur, Taloja and Bhokarpada in the Mumbai region. Under the state's policy, the park must run on at least 51% green power and have two power feeders from independent sources. Operations are due to start in phases from 2028.
It is the second large park under that policy. In September 2025, Lodha signed for a park of about 2.5 GW, with an investment of around Rs 1.3 lakh crore.
Elsewhere, Adani has committed $100 billion to AI infrastructure, including a gigawatt-scale campus with Google in Visakhapatnam and further campuses in Noida, Hyderabad and Pune.
All of these need firm, round-the-clock power from the late 2020s.
Why nuclear, and why small reactors
Solar and wind can supply a large share of a data centre's energy over a year, but not on their own at 2 a.m. on a still night. Covering every hour takes storage, a grid connection backed by thermal plants, or a source that runs continuously. Nuclear is the only carbon-free option that runs day and night without storage.
Until recently, private companies couldn't build it. The SHANTI Act, passed in December 2025, ended six decades of state monopoly. Private companies can now build, own, operate and decommission nuclear plants, and take part in parts of the fuel cycle. The law also kept no-fault liability for operators with mandatory insurance and capped amounts. It removed the operator's automatic right to recover costs from suppliers for defective equipment, which critics say weakens accountability after an accident.
The government has backed this with money and tax changes. The Nuclear Energy Mission has Rs 20,000 crore to get at least five Indian-designed small modular reactors running by 2033. These are units in the 200-220 MWe range, plus a smaller 55 MWe design. Budget 2026-27 removed customs duty on nuclear components. The IT ministry has also looked at SMRs as a power source under a national data centre policy.
Industry interest is broad. Reliance, Tata Power, Adani Power, Hindalco, JSW Energy and Jindal Steel & Power have formally expressed interest in building SMRs. Adani is reported to be in talks with Uttar Pradesh about eight 200 MW units.
The appeal for data centres is clear. A 200 MW reactor next to a campus could provide steady, carbon-free power without relying fully on a congested grid.
The gap between 2028 and 2032
Then there's the timing. Tata Power, one of the most advanced private players, is aiming to start construction in 2028 and commission its first units in 2032-33. As of mid-2026, no binding vendor contracts had been signed. Nuclear projects anywhere rarely finish ahead of schedule.
So the data centre parks arrive from 2028, and the first private reactors arrive after 2032. For four or five years at least, and probably longer for most sites, data centres will run on:
- The grid, which in most states still relies heavily on coal for supply around the clock.
- Renewables with storage, which can meet green-power requirements like Maharashtra's 51% rule but need large battery or pumped-storage capacity to cover every hour.
- Captive or contracted thermal power, used as backup.
Even after 2032, the numbers point to SMRs as one part of the supply, not all of it. One 200 MW reactor covers about a quarter of a 750 MW park, and a fraction of a 2.5 GW one. An "SMR-powered campus" is realistically a campus where a reactor supplies the steady base and the grid and renewables cover the rest.
The questions for policy between now and 2032 are how much new firm capacity states plan for data centre demand, how much of it is clean, and whether transmission to the main data centre clusters (Mumbai, Hyderabad, Delhi NCR, Bengaluru and Chennai) is built in time.
Power is only half of it: the Visakhapatnam dispute
The other limit has nothing to do with megawatts.
In Visakhapatnam, the 1 GW AI campus Google is building with Adani, reported at about $15 billion, faces growing local opposition. The project is planned across three sites in the villages of Tarluvada, Adavivaram and Rambilli. Around 200 of the roughly 500 acres earmarked belongs to Dalit families who were allotted the land in the 1970s, and some have refused to give it up. A court challenge in August failed, and construction continues. Residents have raised concerns about water and electricity use, environmental damage and how few jobs the project will create. One farmer told reporters that the compensation she received, more than $82,000 for two acres, did not reflect the land's real value. Protest posters warn that people "cannot drink data."
Google says the site will use advanced air cooling instead of water, and that the project is a decades-long commitment that will put the local community's interests first. The state government says no water meant for rural or household use will go to data centres. In nearby Vizianagaram district, farmers have separately protested against land acquisition for another proposed data centre.
These concerns don't go away when the power question is solved. A reactor next to a campus would add a safety zone, emergency planning and a new set of local consent questions to the land and water issues already there.
What states will need to get right
Data centre investment in India is now held back less by capital than by two local questions: where the round-the-clock power will come from, and whether the communities around the site accept the project. Neither gets settled by signing an MoU.
The states that attract the next round of investment will be the ones that do this work early:
- Plan firm power before signing. Match each park's expected load with specific generation, storage and transmission, with dates, instead of leaving power supply to be arranged after the MoU.
- Treat nuclear as a long-term option, not a promise. Where SMRs are part of the plan, start site studies, safety-zone mapping and grid planning now, but don't count on reactor power before the 2030s.
- Settle land and water openly. Agree compensation, resettlement and water-use limits with affected communities before construction, and publish them.
- Show the local benefits. Be honest about how many local jobs a data centre creates, which is usually few, and what else the community gets in return, such as power, roads or revenue.
Small reactors may well power a large share of India's data centres in the 2030s. The decisions that determine whether those campuses get built, and whether the people around them accept them, have to be made in the next few years, well before the first reactor is switched on.